Hello,
I checked many same post that ask about the automatic workflow voting like
http://www.aras.com/Community/forums/t/31.aspx
http://www.aras.com/Community/forums/t/1337.aspx
But still I am posting the related post as I was not able to clear doubts.
[ 1 ] Scenario
If the manager of an employee was not able to vote or approve any review task that should be voted automatically after the time [ for example 2 days ] and state of life cycle should be promoted as Auto Approved so one can easily identify that it was approved by system.
[2] Life cycle :- I have created life cycle with following Details
States
- Draft
- Submitted
- Approved
- Auto Approved
[3] Work Flow :-
My doubts regarding the automatic Activity in workflow are
(1) which activity should be set as Automatic Activity
[ In review or Auto Approved ]
(2) What are the Activity Properties to verify the time limit ?
[1] Expected Duration or [2] Time Out Duration
On which Activity this property should be set?
(3) Promotion for submitted to Auto Approved can be trigger on which event
[ on Due ?? ]
(3) in Review have two path here how it will choice the path of Sent for auto Approve ?
(4) How do Aras calculate Due days ? It starts calculating days on the same day of Creation or the day when task will be in in-basket of manager?
Thanks in advance :-)