I have a requirement as follows
There are two project activities. Activity 1 , Activity 2.
Activity 1 is most critical and hence all other activities are dependent on Activity 1.
Activity 2 should finish 7 days before Activity 1 starts.
How do I map this requirement in ARAS PM?